Evergy Inc. submitted a Preconstruction and Prevention of Significant Deterioration (PSD) Air Permit Application for a new simple cycle power plant, named Mullin Creek Generating Station, located in Barnard, Missouri. The department reviewed the application and proposes to issue a PSD Permit to Construct. The department tentatively scheduled a public hearing about the preliminary determination on Dec. 8, 2026.
The department must receive any requests to speak at the hearing by noon, Nov. 27, 2026. The department will cancel this public hearing if no requests to speak are received. Requests to speak at the hearing may be submitted by mail to Stephen Hall, Missouri Department of Natural Resources, Air Pollution Control Program, PO Box 176, Jefferson City, MO 65102-0176, by fax to 573-751-2706 or by email to apcppermitspn@dnr.mo.gov. For more information concerning the hearing, please call the Air Pollution Control Program’s New Source Review unit at 573-751-7726.
The department also is accepting relevant information, materials and views in support of or in opposition to the preliminary decision until Dec. 9, 2026. Please follow the link below for more information about the public comment period, or to review the permit application, preliminary determination and other supporting documents.